Page 20 of 78 FirstFirst ... 10 17 18 19 20 21 22 23 30 ... LastLast
Results 229 to 240 of 934

Thread: Campus Construction

  1. #229

    Default Re: Campus Construction

    New Baker hall on 6-18-11. A precast double "T" floor slab section is being delivered for the parking garage. Less and less material and storage units on this part of the site. They are starting to complete the drainage culverts and inlets. You can really see the difference between the cleaned and uncleaned brick work.

    baker6-18-11

    Cleaning the brick veneer. Note the arches at the entrance. They will be placing concrete for the entry porch soon and then placing decorative columns around the steel in the foreground. The decorative columns are stored on site.

    brick-cleaning


  2. #230

    Default Re: Campus Construction

    Parking garage on 6-18-11

    garage-6-18-11

    Ready to lift a precast double "T" section.

    ready-to-lift

    Flying it into place. Note the guy on the ground with a tag line. Good thing it wasn't too windy today.

    flying

    Almost there and ready to catch.

    catch

    Muscling the section into place. Safety inspector must be off today, he doesn't have his yellow vest on.

    muscle

    There it is.

    done

    They will be building out the middle section and the west section together because the crane won't have enough room to swing.


  3. #231

    Default Re: Campus Construction

    Location of the next piece. A vertical section.

    next-piece

    Here it is. Waiting to be rigged for lifting.

    next-piece2

    Flying into place.

    next-piece3

    There it is. the guy on the manlift is waiting for them to attach and brace so he can remove the rigging. He's not crazy as he has a parasol rigged up for some shade. It was prety hot out there today.

    next-piece4

    It takes about 15 to 20 minutes to rig and place a section. The trucks don't hang around long as there is not much room for them. The driver gets out of the truck only to secure tie downs and blocking. They didn't take time to go to the can.


  4. Default Re: Campus Construction

    This is like a sporting event . . . and UL is winning.

    Thanks for the updates . . . and play by play.


  5. #233

    Default Re: Campus Construction

    Asbestos abatement still going on at the old dorms so not much to show there.

    This is a view of New Huger from Tulane avenue. Hamilton Hall is to the right.

    new-huger-tulane


    View of new Huger at the corner of Tulane Ave and Taft.

    new-huger-taft

    New Baker Hall on June 25, 2011

    A Double "T" section for the parking garage is being delivered in the lower middle. There is less room for the transports to turn around. They may have to start backing in from Taft Street.

    baker6-18-11

    Basket Weave brick work under arch on new Baker Hall.

    new-bake-brick


  6. #234

    Default Re: Campus Construction

    Erection of parking garage precast sections is close to being finished.

    grage-june-25


    Flying in a column section.

    garage-fly-1

    Securing the column section
    garage-secure

    Waiting for a double "T" section. Welder in the background is welding the sections together. There are embed plates in the concrete sections that match up to plates in adjacent sections. They weld them together to secure the building.

    garage-waiting

    Flying in the double "T" section

    garage-fly-2

    Almost there

    garage-almost-there

    Double "T" section in place after a few adjustments.
    garage-there-it-is

    Welding the new section into place to secure it.

    garaage-welding

    View of parking garage as seen from Angelle Hall driveway
    garage-angelle


  7. Default Re: Campus Construction

    Amazing

    Thanks.


  8. #236

    Default Re: Campus Construction

    I have been going on a nightly walk on campus for years. I use the stairs on the Taft Street parking garage for a little extra work. That's how I found the vantage point for the photos I have been taking. Tonight I did the usual walk and when I got to the top of the Taft street parking garage stairs, I noticed that the railing had been hit by one of the concrete sections as they were swinging it into place. It wasn't too bad but I'm sure it got their attention. I was wondering if that was going to happen because they were getting pretty close on Saturday.


  9. #237

    Default Re: Campus Construction

    Serious work this past week.

    New Huger as seen from the Tulane Taft intersection

    new-huger-7-2


    Is the parking temporary or the faculty/staff temporary. Maybe the English Department should proof read all signs in the future.

    grammar-check

    New Baker Hall on July 2, 2077

    baker-7-2

    Finishing up roof vents and and hip caps on New Baker Hall.

    baker-roof

    Entrance to new Baker Hall. Concrete for the porch is placed with brick bases for columns completed. The decorative columns are in the foreground between the man lift and the job shack.

    baker-entrance


  10. #238

    Default Re: Campus Construction

    Erection of the Parking garage was finished on Friday and they are moving the crane out today.

    garage-7-2

    Parking Garage really close to Angelle Hall.

    garage-angelle

    Rigging down the crane used to erect the parking garage. Not much of anything else on the storage yard. I would suspect they will be cleaning up next week. They are placing a new job shack on University avenue to replace the one seen here. D Day for move in is August 11 less than 6 weeks from today.

    rigging-down

    Now that the crane is being moved out they won't require as much room to work. They have promised the band director the field for August 11. I have been told that it will be sodded and sprinkled.


  11. #239

    Default Re: Campus Construction

    Time for monthly comparison

    January 2, 2011

    demo-1

    demo3




    July 2, 2011

    baker-7-2

    garage-7-2


    And they are STILL NOT FINISHED with the softball stadium!!!!


  12. #240

    Default Re: Campus Construction

    Two Words: STATE CONTRACT

    whatever will did will this bid, we must repeat.


Page 20 of 78 FirstFirst ... 10 17 18 19 20 21 22 23 30 ... LastLast

Thread Information

Users Browsing this Thread

There are currently 25 users browsing this thread. (0 members and 25 guests)

Similar Threads

  1. Is that a construction cam?
    By Cajun_RH in forum Up On LA
    Replies: 530
    Last Post: August 29th, 2014, 01:12 pm
  2. UL Campus: Campus Copies cheap, delicious
    By NewsCopy in forum Eats Acadiana
    Replies: 0
    Last Post: September 21st, 2011, 01:56 pm

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •