Nice progress pic posted by Maggard this morning
Thanks. Good pic of progress. Speaking with someone from JB Mouton last week and they commented that they are slightly ahead of schedule. They had to be off the field by this week so they were focused on trying to complete as much as the lower stands as possible since it is more efficient to pour from field level than pump from above. I am not sure if this has been mentioned but the retaining wall on the sidelines has been pushed in 10-15' to get more room on the field. They will do similar on east sideline.
Couple of more pics I saw on facebook this morning
Is the upper deck only half completed? Looks off center and much smaller than pictures. Is it being built in modules?