How are the grandstand seats? Are they narrow like at the dome? Do they have cup holders? I haven't heard anyone complain about them yet. I guess that's a good thing.
What are ya'll thoughts on the progression of the project and the timeline to completion?
Any new pics?
As far as I am concerned there is no rush. We have seats for the games and I don't see us hosting a regional.
It is beautiful now and will only get better.
A lot of the club and suite level sheet rock has been painted inside. The press box outside stucco has been painted as well. Some of the gray metal cladding has been installed above the suites up to the underside of the roof
Looks like they are making good progress on the brick work to the left of the third base line entrance.
Brick arches appear to be taking shape along the third base line bleacher section this morning.