It looks like there's still a lot of work to be done. We're what...11 days out from the home opener? Gonna be a close finish.
First load of brick mortar just arrived. Should get a pretty good day of work in today.
masons on the job.
With good weather, they might be able to finish this week ...
The seating will be ready. They will put as many on that as needed to finish because it is one of the things that need to be done. If it was not going to be done, don't you think they would put more guys on it to finish it. All it takes is bolting seats down to the anchors, so it's not exactly a highly precise or skilled job. They should be able to throw a bunch of guys on it if it gets close
It appears this morning that the majority of the brackets are in place for the grandstand seating. Probably 10-12 workers in the grandstand area this morning. We should see actual seats going in before too long.