On page three.
SCHEDULE:
Phase II Notice to Proceed Date: July 22, 2016
Original Phase II Contract Completion Date: January 31, 2017
Change Order Days Added (scope/weather) N/A
Revised Phase II Contract Completion Date: April 28, 2017
Days Elapsed Since Contract Start: 70 Days
Lemoine Target Schedule Completion Date: April 22, 2017
Contract Time Percent Complete: 27.7%
Adverse Weather Days/Schedule Impact Days Incurred to date: Pending
Ok I see that now. If you look at sheet three the revised contract date is April 28th. The Lemoine target date is April 22nd.
What I am looking at is the "commissioning". Based off what has been said they are trying to get in before everything is "completed". However that isn't happening before life safety systems are tested and signed off on at the commissioning stage.
Bottom line is I think we now have a very solid target completion range. Probably the best we can hope for is April 6th at final commissioning and worst case is April 28th which is the contract date. However its worthy to note that weather days/impact are "pending".
Looks like they are going to work today, Saturday.
I saw two guys meeting yesterday. Looked like they were discussing where to move the web cam. I think one of the problems is finding a place with electricity and won't be affected by the construction. They looked like they were discussing placing it on the mechanical building. It won't be long before all we will be seeing is steel.
Steel workers at it today...on Sunday....
Yes, multiple crews working the beams.
They shut down early. Nothing down after lunch. At least you couldn't see anything. They were looking at the print the rest of the time after lunch. Maybe getting ready for church this evening.