Wrecking forms this morning.
We won't be able to see to much work this week because it will be out of the view of the camera. The do have plenty of work to be done along the first base side of the stadium though. They might get the slab done by next week sometime.
They obviously have more to pour towards the field but I've been wondering how much. Much of that area will be underneath the grandstands and not accessible or visible because it will be walled off. They might just grade out a lot of it and cover with limestone or gravel.
Can somebody check to see if there is a crane on site today.
It's offloading steel this morning
Steel being unloaded today at #TheTigue pic.twitter.com/rNoedRE0zm
— UL Ragin' Cajuns (@ULRaginCajuns) October 24, 2016
Getting close to a hard point on the time line. Looks like they may be starting to erect steel before all of the slab is completed to compress the time line.
There are currently 65 users browsing this thread. (0 members and 65 guests)