Three windows installed third base side of grandstand top floor. Unless that's just plastic covering the opening.
I took a couple of views from across Cajun Field to give you a different perspective to size.
Lights are on. Working on roof.
Looking at the original schedule, the install of aluminum risers were to be completed on Nov. 29, which puts them about 8 weeks off schedule. The final clean for the suites was set to happen Feb. 7. If you use that roughly 8 weeks behind schedule, that could make the suites available around April 7, and all seating areas would be completed for reseating to occur (hopefully before the Easter weekend series). I know they have likely changed the schedule of some things but I think that may give us a rough time line of when all seating areas may be ready. Hopefully this 24 hour schedule was added after the delay and will knock some time off. Any thoughts Helmut?