A few guys working today. Weather eill probably shut them down later today.
A few guys working today. Weather eill probably shut them down later today.
I have my reservations. What are the odds that this will be done by the season end. Are even the South Alabama game, March 31. I know they said that we will play our first home game, March 3, but not in the field of dreams we were hoping for......
If you mean 100% done. It certainly won't be on opening day but it will be done prior to the end of the season. Target date is April 22nd. That may slip due to the fact that we will occupy prior to that date and thus make it more difficult for them to finish but it won't add another month to the schedule.
Let me add that April 22nd is a date given a while back. I' sure there are probably updates from that point.
I'll just say that we will all be better off the day we walk in the stadium in 2017 than the day we walked out in 2016. I'm going to take a guess that the last thing completed is the private suites (because it effects the fewest people and can be isolated). Most of the public areas should be open for our enjoyment for a majority of the season.
I'm one of those people who was walking in with an ice chest and setting up on the third base line in front of the chain link fence. Certainly wasn't a brick wall or patio seats. Been around long before baseball was popular at UL or on the national scene. I've always been amazed at what we have been able to accomplish at this school and the new stadium is mind blowing. College baseball and softball are still sports where the little guy has a chance without being in the billionaire status unlike football and basketball.
After 30 plus years of showing up at the ballpark its kind of fitting that our first game in the new stadium is on my birthday! Happy Birthday to me.... ;-).
April 22 as per the Lemoine timeline. Architect will not say publicly the same because he knows time line can slip. In either case occupancy can occur prior to job completion provided life safety issues and rest room facilities are provided.
Working today. I'm sure it's miserable out there. Misty, damp and a little bit of wind.
Not unusual for concrete placement to dtsrt early in the morning. Especially at this time of year.