Yes they are placing footing concrete now to the right if the camera. They should wreck forms tomorrow and start backfilling. They shpuld continue to work along the first base side.
Yes they are placing footing concrete now to the right if the camera. They should wreck forms tomorrow and start backfilling. They shpuld continue to work along the first base side.
Pouring concrete and stacking steel.
Is it just me, are there is no one working today. Looks like no movement.
The camera was turned somewhat to the left (3rd base) side. It's dark, but you can see the full clubhouse now and very little on the right side where they are still doing concrete work.
This is from Oct. 7. Projected "move-in" date looks to be at the end of April.
Email about meeting with subject "Fabacher Meeting"
End of April?? Doesn't conference tournament begin by late May??
Where is the 16m this project was to cost? Apparently some part of the finish project is left out. Spent so far $1.1m+ and 11.3m+ remaining balance. A total of 12.6+ total cost.
CONTRACT RECAP:
Original Contract Amount $52,319.00
Change Orders Approved $12,607,604.00
Revised Contract Amount $12,659,923.00
Construction Amount Billed to Date $ 1,157,658.72
Cost Percent Complete as of End of Last Month 9.2%
Remaining Construction Balance $ 11,334,958.28
Frenchie I had the same issue when we were discussing the budget a few months back but I finally figured out what was going on. This is construction only and does not include Furnishing, Fixtures & Equipment (FF&E). While that still seems like a lot of money for FF&E it depends on exactly what got put in the FF&E budget. TV's, concessions equipment, and everything to outfit the suites and press box is part of that budget. However it could extend all the way to the actual stadium seats. Bottom line is that is the difference between the 12m I was being told and the 16m others were being told is the FF&E.