Page 27 of 178 FirstFirst ... 17 24 25 26 27 28 29 30 37 ... LastLast
Results 391 to 405 of 2656

Thread: The Building of Russo Park at Louisiana

  1. #391

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by Frenchie35 View Post
    Steel going up:


    Man that's a beautiful site!!!



  2. #392

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by Boomer View Post
    ---Giving me the fresones (SP) Frenchie----pretty soon you will be able to see your seat---BTW do you want it behind home plate or in front of the press box going down 3rd base???
    \

    Behind Home plate. Will look at the seating and make a decision then.

  3. #393

    Default Re: Construction Cam is Up!!!!!!!!

    Looking at the timeline in a little detail this afternoon it looks like we are about six weeks behind the original schedule. The work being done now was originally scheduled for the second week in September. In the original timeline the facility was scheduled to be turned over on the 14th of February. So do the math and that would mean if the original timeline is still the target we are looking at getting into the facility the first week of April.

    Now I don't know if we are still on that timeline or not and I do think there are things that could be done without costing additional money that could get us in a little quicker but we are probably talking a couple of weeks at best. The season kicks off on February 17th this year and based on last years schedule we would be looking for an alternative location for 13 games to get us until the 1st of April or 7 games if we were in mid March.

    Schedule has 10 days weather contingency. We need this dry weather to hold out. Especially up to the point that the project is fully out of the ground. IF weather holds and they squeeze the timeline slightly this thing might not be too bad but there is a lot of room for things to go wrong.


  4. #394

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by Cajun90 View Post
    Looking at the timeline in a little detail this afternoon it looks like we are about six weeks behind the original schedule. The work being done now was originally scheduled for the second week in September. In the original timeline the facility was scheduled to be turned over on the 14th of February. So do the math and that would mean if the original timeline is still the target we are looking at getting into the facility the first week of April.

    Now I don't know if we are still on that timeline or not and I do think there are things that could be done without costing additional money that could get us in a little quicker but we are probably talking a couple of weeks at best. The season kicks off on February 17th this year and based on last years schedule we would be looking for an alternative location for 13 games to get us until the 1st of April or 7 games if we were in mid March.

    Schedule has 10 days weather contingency. We need this dry weather to hold out. Especially up to the point that the project is fully out of the ground. IF weather holds and they squeeze the timeline slightly this thing might not be too bad but there is a lot of room for things to go wrong.
    I was going to do that tonight. I wanted to get to a hard point on the time line and Steel erection was that point. In my previous post in this thread (no 218 on page 11) I had April 3. So it looks like a tight, but doable schedule. I would suspect that if and when they announce a date for occupancy they may add maybe a week to ten days. That way they can say they beat the schedule. Again, I say this with the caveat that we don't know if they re using the same time schedule that was published on the baord back in June. We shall see.

  5. #395

    Default Re: Construction Cam is Up!!!!!!!!

    Eric. Crozier will be on at 7:30.


  6. #396

    Default Re: Construction Cam is Up!!!!!!!!

    My bad will be on at 8:00. You can see the first. Bit of steel in the job cam.


  7. #397

    Default Re: Construction Cam is Up!!!!!!!!

    Right now would be a good time to put in new dugouts.


  8. #398

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by HelmutVII View Post
    My bad will be on at 8:00. You can see the first. Bit of steel in the job cam.
    For those of us that cant listen, I hope someone posts the highlights!

  9. #399

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by LaCajunsFan View Post
    For those of us that cant listen, I hope someone posts the highlights!

    Go here.
    http://1037thegame.com/1037-the-game-audio-on-demand/

  10. #400

    Default Re: Construction Cam is Up!!!!!!!!

    From Eric's interview. The rest of concrete (SOG) should be completed in next couple of weeks. Lemoine working to reduce schedule as much as possible. Some sub contractors out of Baton Rouge were effected by the floods and estimate that set us back 5-6 days. Since that time weather has been great. As of now hope to have majority of steel erection done by around Christmas time. First or second week of February the main stadium (bowl area) should be completed. Upper decks behind existing bleachers will be approximately 30 feet deep.

    They are working on options to occupy prior to completion (as I expected) and talking to code officials and fire marshal to see what could be done to make that happen. That is good to hear because they are obviously trying to plan ahead on a way to get the team and fans in prior to completing everything. I can envision getting occupancy if the main stadium seating area is finished with all life safety issues addressed (handrails, stairwells, exits) but having only partial bathrooms, concessions, pressbox, and suites completed.

    No completion date given other than sometime during the 2017 baseball season. Probably won't be able to predict a really solid date until after the first of the year.


  11. #401

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by cajun tom View Post
    Right now would be a good time to put in new dugouts.
    There was a rumor that was going to happen but when I followed up on it a few months back it seemed to be just that...a rumor.

  12. #402

    Default Re: Construction Cam is Up!!!!!!!!

    Quote Originally Posted by Cajun90 View Post
    From Eric's interview. The rest of concrete (SOG) should be completed in next couple of weeks. Lemoine working to reduce schedule as much as possible. Some sub contractors out of Baton Rouge were effected by the floods and estimate that set us back 5-6 days. Since that time weather has been great. As of now hope to have majority of steel erection done by around Christmas time. First or second week of February the main stadium (bowl area) should be completed. Upper decks behind existing bleachers will be approximately 30 feet deep.

    They are working on options to occupy prior to completion (as I expected) and talking to code officials and fire marshal to see what could be done to make that happen. That is good to hear because they are obviously trying to plan ahead on a way to get the team and fans in prior to completing everything. I can envision getting occupancy if the main stadium seating area is finished with all life safety issues addressed (handrails, stairwells, exits) but having only partial bathrooms, concessions, pressbox, and suites completed.

    No completion date given other than sometime during the 2017 baseball season. Probably won't be able to predict a really solid date until after the first of the year.
    Thanks greatly for the update....I just am not able to listen while at work.

  13. #403

    Default Re: Construction Cam is Up!!!!!!!!

    Really wish they would move the camera so I could see what the hell is going on haha


  14. #404

    Default

    Quote Originally Posted by Cajun90 View Post
    There was a rumor that was going to happen but when I followed up on it a few months back it seemed to be just that...a rumor.
    You sure about that?

    I'm pretty sure I remember reading that a business had donated the money to build new dugouts. Maybe it's not part of the current Tigue project?

  15. #405

    Default Re: Construction Cam is Up!!!!!!!!

    Didn't Whitney buy naming rights of the dugouts for a pretty penny?


Page 27 of 178 FirstFirst ... 17 24 25 26 27 28 29 30 37 ... LastLast

Thread Information

Users Browsing this Thread

There are currently 5 users browsing this thread. (0 members and 5 guests)

Similar Threads

  1. Replies: 0
    Last Post: February 28th, 2019, 03:50 pm
  2. Replies: 1
    Last Post: May 16th, 2018, 06:46 pm
  3. Louisiana Hosts No. 16 LSU at Russo Park
    By NewsCopy in forum Baseball
    Replies: 0
    Last Post: March 6th, 2018, 07:15 pm
  4. Replies: 0
    Last Post: March 4th, 2017, 09:05 pm
  5. Replies: 0
    Last Post: December 13th, 2016, 02:15 pm

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •