If I were to guess, I would say that it will be steps with a railing down the middle. Also if you notice the re-bar ever so often in the pour I think that will be the steps also. That dark grey trash can is on top of one set of re-bar....
If I were to guess, I would say that it will be steps with a railing down the middle. Also if you notice the re-bar ever so often in the pour I think that will be the steps also. That dark grey trash can is on top of one set of re-bar....
The have several pallets of what seams like pavers. Don't know what they are for but will try and find out....
This is the wall separation poured Thursday:
Poured the next level of steps at 5:00 AM this morning. The next pour will be Tuesday. Talked to the engineer on site. He said that the project will start to go faster. They will be working some nights because they prefer it because of the heat during the day. After they have all the seating poured they will start on the concession section while installing the seats. When completed they will start the Athletic center. I saw the prints and it looks like what it shows on the conception drawings. Looks nice. He said it will be completed for Aug. 30 for game time.
Thanks as always! So the elevation won't be the same as the existing seating. I wonder if that is because the East and West sides aren't lined up anyway, so they just split the difference. Or maybe it's the updated codes as was mentioned before
---Frenchie ---How many ramps/stairways do they have on each side--Is that one with only room for about 2 seats---again no idea but would love to see how they are doing it---will there be massive amounts of dirt brought in to do the concessions and bathrooms??? last night at the Tigue was not pretty in the first stall--bad and glad my stay trip to the ____er didn't last for a extended duration--very bad!!!
Thanks for pics & info. Especially nice for those of us who can't swing by for our own look
It just amazes me how engineers and construction workers collaborate together to figure these type of jobs out.. lots of brainpower and labor involved... god bless ya!.....
Boomer I didn't ask that question, but it looks like two on each side of the tunnel. You can see the re-bar on each level of seats where it looks like they will pour a step. If you look on the second picture above the red trash can you can see three sets of re-bar......I think this is where a steps will be poured. Is this what you wanted to know?
There are currently 20 users browsing this thread. (0 members and 20 guests)