They are putting the finial touches on the dirt. Talked to on engineer about the next step. He said that they will be through Wednesday and then they would be pouring a mud slab which is a thin layer of cement over the dirt. He said that they should be pouring it Wednesday.When that is completed and cured they will start on the bottom with the forms and pour each row coming to the top.........
A mud slab is a good idea. I was wondering if they were going to do that. They can dig through it if they have to and not lose a thing.
This bunch of men is getting it done. The engineer that's doing the ground work told me that he wasn't sure what they were going to built but he said that he heard that they was suppose to start in the next month or two. He said that his work was going to be through by Wednesday. I showed him the area of the sports complex and the Cox Communication building and what was planned. He said that must be it. Sounds like a plan to me.
mud slab same thing as soil cement?
Soil cement is a mixture of portland cement and soil. Typically mixed with a stabilizer, a large machine that is an over sized tiller.
A mud slab is somewhat of a misnomer. It is actually a very low strength concrete (low cement content) slab typically 1.5" to 2" thick. It is used to separate the steel and concrete from the dirt or mud and is used to keep the steel clean during the course of setting the steel. It also makes for a safer work site to keep the rod busters from slipping on mud if it rains. Dirt or mud on the rebar is a no no because it acts as a barrier to the concrete adhering to the steel. It also contaminates the structural concrete.
Great...thanks!
Took this at about 1:30 this afternoon.
There are currently 11 users browsing this thread. (0 members and 11 guests)