Pouring the first level???
yup
Those concrete pumper trucks are amazing.
those facilities are going to be built onto the side of a hill. I know the visitors locker room will be built into the hill, but on the other side of the tunnel, are they going to build it on pillars like camps at the point, will it be two story buildings. anyone know that?
You have to love the fact the Cajuns are adding seats at the same Tech is taking apart some of their bleachers.
Now we can see the rate of construction. Today is Tuesday, lets see how long it is between now and the next concrete placement. I'm thinking they need to be placing concrete on the next level by Friday of this week (maybe late Thursday). That will make two rows a week. If they can do that then August deadline is doable with no problem.
Looks like they may get another concrete placement by tomorrow. We shall see. That's one row every 2 days.
I was told that they have pours planed for Thursday and Saturday