They would need to get a good supplier like Whitecap or CMC. Big guys that can handle a job like this quickly. They have computer driven automatic rebar benders that can bend a bar exactly the same way every time fairly quickly. I would think they could get rebar on site in about 4 to 6 weeks after final approval of shop drawings and detail sheets. The problem is if an error is made in detailing and it's not caught then they could literally have tons of bent rebar that they can't use. I am glad I am not involved in that. Given that, I would suspect they have a good 6 to eight weeks of dirt work and form work to do so they can probably schedule around it.

I was thinking DD would have been finished in early January and they would be finishing finals now. I'm sure they are putting in some long hours on this one. That kind of scares me a little bit because that's when errors happen. We shall see.

they can make up time by turning on the lights and running two shifts.