Went to the field today. They hauled in more underlayment. Talked to a UL engineer there and he said that he thought the goal post would be in place today. Usually they put the post first that roll out the fabric next. But they may do it after the turf is down. The next step is to lay down the thin fabric than the 2" rubber fabric. Than the truf. He said that the job should be completed by July 5.....That's about right because it takes two week to roll out the liner, rubber fabric and turf and paint same....so July 5 looks right. When they start this process I will document it on film and post same.
Frenchie