2 Attachment(s)
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
Frenchie35
So the Cox building will be taken down before the new Clubhouse is built therefore the coach and players will have to move out of the Cox building when the roof is sealed around the columns that will go through the old clubhouse......Please don't advertise this because the school to the east of us and the one to the north of us.....way north, will have a field day on that plan.
Attachment 12100Attachment 12101
Frenchie, Ruston won't be making fun of anything. Their new football locker room is a maze with all the columns in it. There's more, these are just the only 2 pics I took....
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
LaCajunsFan
Is Helmut the 'resident engineer?' I don't think I've seen a definitive date from him, although right above he says he's not sure how much of the season will be lost.
The only reason I am not sure is because I don't know exactly where they are on the time line. Once they finish with the slab on grade that will give me a hard point and then I can compare that point with the same point on original time line. What I do know is they had originally projected completion of the demolition at the end of June and from what I can tell they finished demolition in the first week of August. That puts them about 5 weeks behind the original time line. What I don't know is what affect the rains in August had on the work schedule. I suspect at least a week but that's a guess.
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
HelmutVII
The only reason I am not sure is because I don't know exactly where they are on the time line. Once they finish with the slab on grade that will give me a hard point and then I can compare that point with the same point on original time line. What I do know is they had originally projected completion of the demolition at the end of June and from what I can tell they finished demolition in the first week of August. That puts them about 5 weeks behind the original time line. What I don't know is what affect the rains in August had on the work schedule. I suspect at least a week but that's a guess.
Understood....but that's my point: we certainly all agree that there was a significant delay, but we really don't have a firm grasp yet of how delayed we are. And I for one will believe you, once you are able to make that projection.
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
duggie85
Attachment 12100Attachment 12101
Frenchie, Ruston won't be making fun of anything. Their new football locker room is a maze with all the columns in it. There's more, these are just the only 2 pics I took....
But....those aren't columns.....they are racks to hold up all those nifty tv screens. LOL
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
no1cajunfan
Link does not work today.
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
duggie85
Attachment 12100Attachment 12101
Frenchie, Ruston won't be making fun of anything. Their new football locker room is a maze with all the columns in it. There's more, these are just the only 2 pics I took....
Looks like the laundry room for the most part.
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
Frenchie35
Link does not work today.
The whole ragincajuns.com website has been down this morning.
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
Cajun90
The whole ragincajuns.com website has been down this morning.
Website is back up and they did indeed make a pour this morning. Progress....
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
HelmutVII
The only reason I am not sure is because I don't know exactly where they are on the time line. Once they finish with the slab on grade that will give me a hard point and then I can compare that point with the same point on original time line. What I do know is they had originally projected completion of the demolition at the end of June and from what I can tell they finished demolition in the first week of August. That puts them about 5 weeks behind the original time line. What I don't know is what affect the rains in August had on the work schedule. I suspect at least a week but that's a guess.
It rained in August? You sure?
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
Cajun90
Website is back up and they did indeed make a pour this morning. Progress....
They quit working after the pour or because there's a football game tonight at 7:00 PM?
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
Frenchie35
They quit working after the pour or because there's a football game tonight at 7:00 PM?
I'd guess they poured all of the footings and would have to wait for them to cure which may take a couple of days. Helmut?
Re: Construction Cam is Up!!!!!!!!
Quote:
Originally Posted by
CajunAmos
I'd guess they poured all of the footings and would have to wait for them to cure which may take a couple of days. Helmut?
They will probably wreck the forms tomorrow and move them over to the next section.